Be aware of fall construction on Lincoln Avenue in Downtown Steamboat


The Colorado Department of Transportation (CDOT) has issued a utility permit for work on
Lincoln Avenue between 4th Street and Old Fish Creek Falls Road. Between Tuesday,
September 2nd and Saturday, November 15th, construction crews will be working within
Lincoln Avenue as they upgrade public water, sanitary sewer, and storm sewer
infrastructure.

During this time there will be varying detours as they try to accomplish the work safely,
quickly, and with the least amount of disruption feasible. Periodic updates will be provided
on the City Page as work progresses.

The first phase of work will involve installation of a new box culvert and a new sanitary
sewer on the west side of Lincoln Avenue near the Blimpie's restaurant, and should last
two to three weeks. You will notice lane shifts to accommodate the work.

Two lanes of traffic in each direction will be maintained during daylight hours throughout
the project. Congestion is anticipated, and alternate routes are advised.
For more information, please contact Jeff Johnson, Project Manager, Calcon Constructors
at (303) 762-1554 or Greg Gunn, Construction Site Inspector, City of Steamboat Springs
(970) 871-8273.
###
For information contact:
Jeff Johnson, Project Manager, Calcon Constructors (303) 762-1554
Greg Gunn, Construction Site Inspector, City of Steamboat Springs (970) 871-8273